As part of the project for the installation of the electricity storage system at the Okroglo substation, electrical installation work is currently underway. Medium and low voltage equipment was delivered on-site and will be installed in the next three weeks.
Construction work is temporarily suspended, as outside temperatures do not allow for the completion of construction work. Namely, it is still necessary to complete the final backfill, lay curbs and asphalt and arrange the surroundings.